Not legal advice. No template is compliant out of the box. A SWMS has to be made site-specific with the workers doing the job before work starts. SWMS Kit is not a regulator.

Electrician SWMS Kit · SWMS 03

Switchboard installation, upgrade and energised testing

New boards, upgrades and the testing that has to happen when a board is energised — including old boards that may contain asbestos.

Ships as two files: Model WHS (NSW, QLD, SA, TAS, ACT, NT, WA) and a Victorian OHS version. Model (k), and (d) if asbestos is likely. Victorian 7 and 16. Not compliant until you make it specific to the site with the workers doing the work.

Collage of real page screenshots from the Electrician SWMS Kit
The pack at a glance — real pages, not a mockup.

What the task table covers

  • Inspect the existing board before touching it. Asbestos in older boards and backing, damaged live parts
  • Install or upgrade the board dead. Stored energy, incoming mains still live, sharp edges
  • Test and energise. Wrong polarity, loose terminations, arc on switch-on
  • Hand the board over. Next trade treats a half-finished board as safe

Asbestos awareness sits on this SWMS. It is not a removal licence.